  • Question 281:

    If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

    A. Senior User

    B. Executive

    C. Corporate/programme management

    D. Senior Supplier

  • Question 282:

    In what process is the authorization to deliver the project's products given?

    A. Starting up a Project

    B. Initiating a Project

    C. Managing a Stage Boundary

    D. Directing a Project

  • Question 283:

    Which of the following is NOT part of quality planning?

    A. Define quality responsibilities

    B. Gain acceptance of the project product

    C. Agree acceptance criteria

    D. Set quality tolerances

  • Question 284:

    Which should be provided by a project mandate?

    A. Terms of reference

    B. Detailed Business Case

    C. Stage tolerances

    D. Initiation Stage Plan

  • Question 285:

    Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.

    A. the measurement of benefits NOT yet realized

    B. the handover of products

    C. open issues and risks

    D. the release of resources

  • Question 286:

    Which is the purpose of the Change theme?

    A. Prevent change to baselined products

    B. Identify, assess and control any potential and approved changes to baselined products

    C. Establish mechanisms to monitor and compare actual achievements against those planned

    D. Assess and control uncertainty

  • Question 287:

    Why is a Project Brief produced?

    A. To act as a trigger for the Starting up a Project process

    B. To record the strategies and management controls to be used by a project

    C. To provide a full and firm foundation for the initiation of a project

    D. To be used by the Project Board as a basis for reviewing the progress of a project

  • Question 288:

    Which of the following statements about the Project Initiation Documentation are true?

    1.

    The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project.

    2.

    The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project.

    A. Only 1 is true

    B. Only 2 is true

    C. Both 1 and 2 are true

    D. Neither 1 or 2 are true

  • Question 289:

    Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

    A. Risk category

    B. Risk description

    C. Risk response

    D. Risk status

  • Question 290:

    If an informal issue is defined as a problem or concern, where should it first be recorded?

    A. Issue Register

    B. Risk Register

    C. Daily Log

    D. Exception Report

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.