Which set of tools and techniques is useful for estimating activity durations for the project schedule?
A. Brainstorming, Monte Carlo Simulation, analogous estimation
B. Three-point estimation, resources leveling, iteration burndown chart
C. Milestone charts, parametric estimation, schedule baseline
D. Parametric estimation, three-point estimation, analogous estimation
In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage.
How will the project team determine project cost?
A. Use a lightweight cost estimation due to the nature of agile projects
B. Use a detailed cost estimation for agile projects
C. Retrieve a budget from a previous project and create a baseline for this project based on it
D. Use a detailed work breakdown structure (WBS) to get cost estimation
Which statement about identification and engagement of stakeholders during a project is correct?
A. Project stakeholders should be identified and engaged in every phase of the project to influence the success of the project directly.
B. Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.
C. Project stakeholders should be identified when the project charter is being completed and engaged during requirements gathering.
D. Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process
What are the two most common contract types used in a project?
A. Cost plus award fee (CPAF) contract and fixed price contract
B. Fixed price contract and cost-reimbursable contract
C. Cost-reimbursable contract and time and material (TandM) contract
D. Time and material (TandM) contract and cost plus award fee (CPAF) contract
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
A. A diagram in which resource optimization has been applied
B. A diagram in which the critical path method has been applied
C. A diagram in which a predefined series of activities has been organized
D. A diagram which shows a combination of resource and time optimization
A project is in the planning phase. The project manager is considering different elements that may influence or constrain the project.
Which of the following internal enterprise environmental factors should the project manager consider?
A. Industry standards
B. Market conditions
C. Legal restrictions
D. Employee capability
Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?
A. Project charter, business documents, and project management plan
B. Agreements, scope baseline, and project management plan
C. Project charter, business case, and project management plan
D. Work performance data, enterprise environmental factors, and project management plan
Which of the following documents are created as part of Project Integration Management?
A. Project charter and project management plan
B. Communications management plan and scope management plan
C. Quality management plan and risk management plan
D. Project scope statement and communications management plan
A junior team member has been promoted to the position of project manager. The first task to execute is the Quality Management Plan.
Which tools and techniques will help the project manager to complete this task?
A. Benchmarking, design of experiments, and cost-benefit analysis
B. Quality audits, process analysis, and meetings
C. Inspection, brainstorming, and quality audits
D. Networking, brainstorming, and negotiation
The project manager has the following information about the estimated duration for an activity:
Most likely [tM] – 15 days
Pessimistic [tP] – 20 days
Optimistic [tO] – 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
A. 10 days
B. 15 days
C. 12.5 days
D. 5 days
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.