PMI CAPM PMI-100 Questions & Answers

  • Question 81:

    A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

    A. Urgent information need

    B. Sensitivity of information

    C. Project environment

    D. Ease of use

  • Question 82:

    Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

    A. Organizational process updates

    B. Quality metrics

    C. Change requests

    D. Quality control measurements

  • Question 83:

    A temporary endeavor that creates a unique product or service is called a:

    A. Project

    B. Plan

    C. Program

    D. Portfolio

  • Question 84:

    Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

    A. Earned value management.

    B. Enterprise environmental factors.

    C. Organizational process assets.

    D. Work performance information.

  • Question 85:

    An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

    A. smooth/accommodate

    B. force/direct

    C. collaborate/problem solve

    D. compromise/reconcile

  • Question 86:

    The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

    A. Continuous improvement.

    B. Predictive planning.

    C. Progressive elaboration.

    D. Quality assurance.

  • Question 87:

    Which grid shows which resources are tied to work packages?

    A. Work breakdown structure (WBS)

    B. Responsibility assignment matrix (RAM)

    C. Project assignment chart

    D. Personnel assignment matrix

  • Question 88:

    Typical outcomes of a project include:

    A. Products, services, and improvements.

    B. Products, programs, and services.

    C. Improvements, portfolios, and services.

    D. Improvements, processes, and products.

  • Question 89:

    When does the project team determine which dependencies are discretionary?

    A. Before the Define Activities process

    B. During the Define Activities process

    C. Before the Sequence Activities process

    D. During the Sequence Activities process

  • Question 90:

    A project manager builds consensus and overcomes obstacles by employing which communication technique?

    A. Listening

    B. Facilitation

    C. Meeting management

    D. Presentation

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.