Stakeholder satisfaction should be managed as a key project:
A. Benefit
B. Initiative
C. Objective
D. Process
Which Knowledge Areas include processes from the Closing Process Group?
A. Project Quality Management and Project Time Management
B. Project Scope Management and Project Risk Management
C. Project Stakeholder Management and Project Cost Management
D. Project Integration Management and Project Procurement Management
In a project, total float measures the:
A. Ability to shuffle schedule activities to lessen the duration of the project.
B. Amount of time an activity can be extended or delayed without altering the project finish date.
C. Cost expended to restore order to the project schedule after crashing the schedule.
D. Estimate of the total resources needed for the project after performing a forward pass.
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
A. Customers.
B. Business partners.
C. Sellers.
D. Functional managers.
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A. Develop Schedule
B. Create VVBS
C. Estimate Activity Resources
D. Define Scope
An output of the Direct and Manage Project Work process is:
A. Deliverables.
B. Activity lists.
C. A work breakdown structure.
D. A scope statement.
An input to Close Project or Phase is:
A. Accepted deliverables.
B. Final products or services.
C. Document updates.
D. Work performance information.
Which tool or technique is used in validating the scope of a project?
A. Facilitated workshops
B. Interviews
C. Inspection
D. Meetings
The process of prioritizing risks for further analysis or action is known as:
A. Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.
The number of potential communication channels for a project with 5 stakeholders is:
A. 10.
B. 12.
C. 20.
D. 24.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.