Which Control Quality tool is also known as an arrow diagram?
A. Matrix diagram
B. Affinity diagram
C. Tree diagram
D. Activity network diagram
The Monitoring and Controlling Process Group includes processes that:
A. Establish the scope, objectives, and course of action of a project.
B. Define a new project or a new phase of an existing project.
C. Track, review, and regulate the progress and performance of a project.
D. Complete the work defined in the project management plan.
Sensitivity analysis is typically displayed as a/an:
A. Decision tree diagram.
B. Tornado diagram.
C. Pareto diagram.
D. Ishikawa diagram.
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
A. External
B. Internal
C. Mandatory
D. Discretionary
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
A. Cost management plan.
B. Work performance information.
C. Quality management plan.
D. Work breakdown structure.
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
A. Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
A. Only once, at the beginning
B. At the beginning and the end
C. Once during each phase
D. Repeatedly
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
A. A risk urgency assessment.
B. The scope baseline.
C. Work performance information.
D. Procurement audits.
Which tool or technique is used to develop the human resource management plan?
A. Ground rules
B. Expert judgment
C. Team-building activities
D. Interpersonal skills
What are the Project Procurement Management processes?
A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.