Exam Details

  • Exam Code
    :PMI-100
  • Exam Name
    :Certified Associate in Project Management(CAPM)
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :1073 Q&As
  • Last Updated
    :May 13, 2025

PMI CAPM PMI-100 Questions & Answers

  • Question 741:

    The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

    A. Project

    B. Scope

    C. Contract

    D. Program

  • Question 742:

    Which baselines make up the performance measurement baseline?

    A. Scope baseline, cost baseline, and schedule baseline

    B. Scope baseline, project management baseline, and quality baseline

    C. Cost baseline, schedule baseline, and risk baseline

    D. Cost baseline, project management baseline, and schedule baseline

  • Question 743:

    The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

    A. a control chart.

    B. baseline.

    C. Create WBS.

    D. decomposition.

  • Question 744:

    Which of the following is an output of the Conduct Procurements process?

    A. Project statement of work

    B. Selected sellers

    C. Risk register updates

    D. Teaming agreements

  • Question 745:

    The three processes of Project Cost Management are:

    A. Estimate Costs, Control Schedule, and Control Costs.

    B. Estimate Costs, Determine Budget, and Estimate Activity Resources.

    C. Determine Budget, Control Schedule, and Estimate Activity Resources.

    D. Estimate Costs, Determine Budget, and Control Costs.

  • Question 746:

    Which risk response strategy is common for both positive and negative risks?

    A. Share

    B. Accept

    C. Mitigate

    D. Transfer

  • Question 747:

    Risk responses reflect an organization's perceived balance between:

    A. risk taking and risk avoidance.

    B. known risk and unknown risk.

    C. identified risk and analyzed risk.

    D. varying degrees of risk.

  • Question 748:

    After Define Activities and Sequence Activities, the next process is:

    A. Estimate Activity Resources.

    B. Estimate Activity Durations.

    C. Develop Schedule.

    D. Control Schedule.

  • Question 749:

    The correct equation for schedule variance (SV) is earned value:

    A. minus planned value [EV - PV].

    B. minus actual cost [EV - AC].

    C. divided by planned value [EV/PV],

    D. divided by actual cost [EV/AC].

  • Question 750:

    Which of the following is an output of Define Scope?

    A. Project scope statement

    B. Project charter

    C. Project plan

    D. Project schedule

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.