Exam Details

  • Exam Code
    :PMI-100
  • Exam Name
    :Certified Associate in Project Management(CAPM)
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :1073 Q&As
  • Last Updated
    :May 13, 2025

PMI CAPM PMI-100 Questions & Answers

  • Question 731:

    Which type of dependency is contractually required or inherent in the nature of the work?

    A. External

    B. Lead

    C. Discretionary

    D. Mandatory

  • Question 732:

    Which of the following includes how requirements activities will be planned, tracked, and reported?

    A. Configuration management plan

    B. Scope baseline

    C. Requirements management plan

    D. Schedule baseline

  • Question 733:

    Which statement correctly describes the value of a business case?

    A. It provides the necessary information to determine if a project is worth the required investment.

    B. It provides for alternative dispute resolution procedures in event of contract default.

    C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

    D. It is used to help a project manager understand the scope of commercial advantages.

  • Question 734:

    Which of the following is a group decision-making technique?

    A. Brainstorming

    B. Focus groups

    C. Affinity diagram

    D. Plurality

  • Question 735:

    Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

    A. Acquisition

    B. Negotiation

    C. Virtual team

    D. Pre-assignment

  • Question 736:

    While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

    A. Communications management plan

    B. Human resource plan

    C. Quality management plan

    D. Procurement management plan

  • Question 737:

    One of the objectives of a quality audit is to:

    A. highlight the need for root cause analysis.

    B. share the process documentation among stakeholders.

    C. offer assistance with non-value-added activities.

    D. identify all of the gaps or shortcomings.

  • Question 738:

    A tool and technique used during the Collect Requirements process is:

    A. prototypes.

    B. expert judgment.

    C. alternatives identification.

    D. product analysis.

  • Question 739:

    Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

    A. Estimate at completion

    B. Cost performance

    C. Schedule performance

    D. To-complete performance

  • Question 740:

    Prototype development may be used as a tool for which of the following risk response strategies?

    A. Avoid

    B. Accept

    C. Mitigate

    D. Exploit

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.