Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
A. manager.
B. success.
C. deadline.
D. scope.
Which of the following response strategies are appropriate for negative risks or threats?
A. Share, Accept, Transfer, or Mitigate
B. Exploit, Enhance, Share, or Accept
C. Mitigate, Share, Avoid, or Accept
D. Avoid, Mitigate, Transfer, or Accept
A tool and technique used during the Define Scope process is:
A. facilitated workshops.
B. observations.
C. questionnaires and surveys.
D. group creativity techniques.
The process for performing variance analysis may vary, depending on:
A. scenario building, technology forecasting, and forecast by analogy.
B. working relationships among various stakeholders and team members.
C. application area, the standard used, and the industry, D. work to be completed next.
The risk shared between the buyer and seller is determined by the:
A. assumption log.
B. quality checklist.
C. risk register.
D. contract type.
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
A. operate separately.
B. move together in batches,
C. overlap and interact.
D. move in a sequence.
Which of the following is a tool or technique used in the Determine Budget process?
A. Variance analysis
B. Three-point estimating
C. Bottom-up estimating
D. Historical relationships
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
A. event.
B. response.
C. perception.
D. impact.
Plan-do-check-act is also known as:
A. prevention over inspection.
B. statistical sampling.
C. management responsibility,
D. continuous improvement.
The total of the planned value (PV) is also known as:
A. work breakdown structure (WBS).
B. schedule target.
C. performance measurement baseline (PMB).
D. earned value baseline.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.