  • Question 31:

    When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

    A. improvement

    B. program

    C. result

    D. portfolio

  • Question 32:

    Which tools or techniques are used during the Close Project or Phase process?

    A. Reserve analysis and expert judgment

    B. Facilitation techniques and meetings

    C. Expert judgment and analytical techniques

    D. Performance reviews and meetings

  • Question 33:

    Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

    A. organizational skills

    B. technical skills

    C. communication skills

    D. hard skills

  • Question 34:

    A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

    A. Plan Stakeholder Management

    B. Identify Stakeholders

    C. Manage Stakeholder Engagement

    D. Control Stakeholder Engagement

  • Question 35:

    While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

    A. ends.

    B. begins.

    C. delays.

    D. deviates.

  • Question 36:

    Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

    A. Activity cost estimates

    B. Earned value management

    C. Cost management plan

    D. Cost baseline

  • Question 37:

    Specification of both the deliverables and the processes is the focus of:

    A. Change control

    B. Configuration control

    C. Project monitoring and control

    D. Issue control

  • Question 38:

    The following is a network diagram for a project.

    The free float for Activity E is how many days?

    A. 2

    B. 3

    C. 5

    D. 8

  • Question 39:

    Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

    A. Smooth/accommodate

    B. Withdraw/avoid

    C. Compromise/reconcile

    D. Force/direct

  • Question 40:

    The following is a network diagram for a project.

    The total float for the project is how many days?

    A. 5

    B. 9

    C. 12

    D. 14

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.