Exam Details

  • Exam Code
    :PMI-100
  • Exam Name
    :Certified Associate in Project Management(CAPM)
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :1073 Q&As
  • Last Updated
    :May 10, 2024

PMI CAPM PMI-100 Questions & Answers

  • Question 21:

    Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

    A. Continuous

    B. Discrete

    C. Regulated

    D. Arbitrary

  • Question 22:

    The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

    A. recognition and rewards

    B. compliance

    C. staff acquisition

    D. training needs

  • Question 23:

    The following is a network diagram for a project.

    The critical path for the project is how many days in duration?

    A. 10

    B. 12

    C. 14

    D. 17

  • Question 24:

    The following is a network diagram for a project.

    The shortest non-critical path for the project is how many days in duration?

    A. 10

    B. 12

    C. 14

    D. 16

  • Question 25:

    Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

    A. Influencing

    B. Motivation

    C. Negotiation

    D. Trust building

  • Question 26:

    Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

    A. Procurement documents

    B. Inspection and audits

    C. Estimate budget

    D. Risk register

  • Question 27:

    An example of a group decision-making technique is:

    A. nominal group technique

    B. majority

    C. affinity diagram

    D. multi-criteria decision analysis

  • Question 28:

    Which type of graphic is displayed below?

    A. Work breakdown structure

    B. Context diagram

    C. Control chart

    D. Pareto diagram

  • Question 29:

    The zero duration of milestones in project planning occurs because milestones:

    A. Are unpredictable and challenge the Plan Schedule Management process.

    B. Occur at random times in the project plans.

    C. Represent a moment in time such as a significant project point or event.

    D. Represent both significant and insignificant points in the project and are difficult to anticipate.

  • Question 30:

    The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

    A. management

    B. response

    C. tolerance

    D. appetite

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.