Exam Details

  • Exam Code
    :PMI-100
  • Exam Name
    :Certified Associate in Project Management(CAPM)
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :1073 Q&As
  • Last Updated
    :May 05, 2025

PMI CAPM PMI-100 Questions & Answers

  • Question 1051:

    After defining activities in project schedule management, which processes should a project manager follow?

    A. Sequence Activities and Estimate Activity Durations

    B. Estimate Activity Durations and Control Schedule

    C. Develop Schedule and Control Schedule

    D. Review Activities and Develop Schedule

  • Question 1052:

    Which is the order of steps in the Procurement Management process?

    A. Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements.

    B. Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements.

    C. Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors.

    D. Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements.

  • Question 1053:

    Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem.

    Which technique should the project manager use?

    A. Withdraw/Avoid

    B. Smooth/Accommodate

    C. Compromise/Reconcile

    D. Collaborate/Problem Solve

  • Question 1054:

    Which of the following set of elements is part of an effective communications management plan?

    A. Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information.

    B. Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology.

    C. Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology.

    D. Glossary of common terminology, constraints derived from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan.

  • Question 1055:

    The project team is using their current information, abilities, and experience to achieve project objectives; the team is also developing new experiences, and the project manager is ensuring that the team is documenting new learnings in order to contribute to organizational knowledge.

    In which process is the project team and project manager involved?

    A. Direct and manage project work

    B. Manage project knowledge

    C. Develop team

    D. Manage team

  • Question 1056:

    Given the following information:

    Activity A takes one week.

    Activity B takes three weeks.

    Activity C takes two weeks.

    Activity D takes five weeks.

    Activity A starts at the same time as Activity B.

    Activity C follows Activity B and Activity A.

    Activity D follows Activity C.

    How long will it take to complete the project?

    A. 8 weeks

    B. 9 weeks

    C. 10 weeks

    D. 11 weeks

  • Question 1057:

    Which are the competing constraints that a project manager should address when tailoring a project?

    A. Cost, scope, schedule

    B. Sponsorship, risk, quality

    C. Schedule, sponsorship, scope

    D. Resources, quality, communication

  • Question 1058:

    The activity of tailoring is necessary because:

    A. The members of the project team is need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide; this is required for all projects.

    B. Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.

    C. The members of the project team need to understand the PMBOK Guide processes, which are applied to all projects.

    D. Each project is unique, and the project team must plan how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide.

  • Question 1059:

    Which conflict resolution technique is based on bringing some degree of satisfaction to all parties?

    A. Smooth/Accommodate

    B. Collaborate/Problem Solve

    C. Compromise/Reconcile

    D. Withdraw/Avoid

  • Question 1060:

    What are the four management processes included in the Project Cost Management (PCM) method?

    A. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs

    B. Control Costs, Project Cost Management, Determine Budget, Estimate Costs

    C. Estimate Activities, Control Costs, Project Cost Management, Determine Budget

    D. Control Quality, Project Cost Management, Estimate Costs, Determine Budget

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.