  • Question 111:

    The process of identifying and documenting relationships among the project activities is known as:

    A. Control Schedule.

    B. Sequence Activities.

    C. Define Activities.

    D. Develop Schedule.

  • Question 112:

    The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

    A. Human resource management plan.

    B. Activity resource requirements.

    C. Personnel assessment tools,

    D. Multi-criteria decision analysis.

  • Question 113:

    A key benefit of the Manage Communications process is that it enables:

    A. The best use of communication methods.

    B. An efficient and effective communication flow.

    C. Project costs to be reduced.

    D. The best use of communication technology.

  • Question 114:

    Lessons learned are created and project resources are released in which Process Group?

    A. Planning

    B. Executing

    C. Closing

    D. Initiating

  • Question 115:

    When should quality planning be performed?

    A. While developing the project charter

    B. In parallel with the other planning processes

    C. As part of a detailed risk analysis

    D. As a separate step from the other planning processes

  • Question 116:

    Which tool or technique is used in the Develop Project Management Plan process?

    A. Project management information system (PMIS)

    B. Project charter

    C. Quality assurance

    D. Expert judgment

  • Question 117:

    Which process involves developing an approximation of the monetary resources needed to complete project activities?

    A. Estimate Costs

    B. Control Costs

    C. Determine Budget

    D. Plan Cost Management

  • Question 118:

    The ability to influence cost is greatest during which stages of the project?

    A. Early

    B. Middle

    C. Late

    D. Completion

  • Question 119:

    In which Knowledge Area is the project charter developed?

    A. Project Cost Management

    B. Project Scope Management

    C. Project Time Management

    D. Project Integration Management

  • Question 120:

    The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

    A. Work packages.

    B. Accepted deliverables.

    C. The WBS dictionary.

    D. The scope baseline.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.