  • Question 421:

    Where are product requirements and characteristics documented?

    A. Product scope description

    B. Project charter

    C. Preliminary project scope statement

    D. Communications management plan

  • Question 422:

    What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

    A. Organizational process assets

    B. Enterprise environmental factors

    C. Project management processes

    D. Project scope management plan

  • Question 423:

    Manage Project Team belongs to which knowledge area?

    A. Project Integration Management

    B. Project Time Management

    C. Project Procurement Management

    D. Project Human Resource Management

  • Question 424:

    Who must accept the end product for a project to be considered closed?

    A. Project team

    B. Project manager

    C. Project management office

    D. Customer or sponsor

  • Question 425:

    How many process groups are there according to the PMBOK Guide?

    A. 5

    B. 9

    C. 10

    D. 12

  • Question 426:

    The Monitoring and Controlling process group contains which of the following processes?

    A. Plan Quality

    B. Perform Quality Assurance

    C. Perform Quality Control

    D. Identify Stakeholders

  • Question 427:

    Which process group establishes the total scope of a project?

    A. Initiating

    B. Planning

    C. Monitoring and Controlling

    D. Executing

  • Question 428:

    Which process group defines the course of action required to attain the objectives that the project was undertaken to achieve?

    A. Initiating

    B. Executing

    C. Planning

    D. Monitoring and Controlling

  • Question 429:

    Perform quality assurance belongs to which of the following process groups?

    A. Planning

    B. Executing

    C. Monitoring and Control

    D. Closing

  • Question 430:

    A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?

    A. Closing

    B. Executing

    C. Monitoring and Controlling

    D. Planning

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.