  • Question 441:

    A project manager has limited authority in which type of organizational structure?

    A. Weak matrix

    B. Functional

    C. Balanced matrix

    D. Projectized

  • Question 442:

    Which of the following is an input to direct and manage project execution?

    A. Requested changes

    B. Approved preventive action

    C. Work performance information

    D. Implemented defect repair

  • Question 443:

    Which is a true statement regarding project governance?

    A. Project governance approach must be described in the project management plan.

    B. Project governance is independent of the organization or program sponsoring it.

    C. Once a project has begun, it is not necessary to formally initiate each project phase.

    D. Review of project performance and key deliverables is not required for each project phase.

  • Question 444:

    What are three basic types of project phase-to-phase relationships?

    A. Sequential, Overlapping, Non-overlapping

    B. Sequential, Iterative, Overlapping

    C. Sequential, Non-overlapping, Iterative

    D. Iterative, Overlapping, Non-overlapping

  • Question 445:

    In which type of organization does a project manager have a moderate-to-high resource availability?

    A. Functional

    B. Weak

    C. Balanced

    D. Strong

  • Question 446:

    Which stakeholder is responsible for managing related projects in a coordinated way?

    A. Sponsor

    B. Portfolio manager

    C. Program manager

    D. Project manager

  • Question 447:

    In which of the following organizational structures does the project manager have full authority on a project?

    A. Functional

    B. Strong matrix

    C. Balanced matrix

    D. Projectized

  • Question 448:

    Company A is delivering a product in three parts. The contract allows for the parts to be delivered either one after the other or at the same time. Which type of project phasing will allow for the most flexibility in delivering the full product when product requirements are subject to rapid change?

    A. Sequencing the delivery phases one after the other

    B. Overlapping the delivery phases

    C. Delivering the products iteratively

    D. Delivering all of the product at the same time

  • Question 449:

    At which point of the project is the uncertainty the highest and the risk of failing the greatest

    A. Final phase of the project

    B. Start of the project

    C. End of the project

    D. Midpoint of the project

  • Question 450:

    When do stakeholders have the greatest influence?

    A. At the start of the project

    B. At the end of the project

    C. During execution

    D. Stakeholders have constant influence

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.