  • Question 411:

    What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

    A. Decomposition

    B. Benchmarking

    C. Inspection

    D. Checklist analysis

  • Question 412:

    Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

    A. WBS directory

    B. Activity list

    C. WBS

    D. Project schedule

  • Question 413:

    What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

    A. Organizational Breakdown Structure (OBS)

    B. Work Performance Information

    C. Work Package

    D. Work Breakdown Structure (WBS)

  • Question 414:

    What component of the project scope definition defines project exclusions?

    A. Project boundaries

    B. Project constraints

    C. Project assumptions

    D. Project objectives

  • Question 415:

    What type of project structure is a hierarchically organized depiction of the resources by type?

    A. Organizational Breakdown Structure (OBS)

    B. Resource Breakdown Structure (RBS)

    C. Work Breakdown Structure (WBS)

    D. Project Breakdown Structure (PBS)

  • Question 416:

    What causes replanning of the project scope?

    A. Requested changes

    B. Project scope statement changes

    C. Variance analysis

    D. Approved change requests

  • Question 417:

    What scope definition technique is used to generate different approaches to execute and perform the work of the project?

    A. Build vs. buy

    B. Expert judgment

    C. Alternatives identification

    D. Product analysis

  • Question 418:

    The scope management plan is a subsidiary of which project document?

    A. Schedule management plan

    B. Project management plan

    C. Quality management plan

    D. Resource management plan

  • Question 419:

    Which of the following is an input to the Direct and Manage Project Execution Process?

    A. Approved corrective actions

    B. Approved contract documentation

    C. Work performance information

    D. Rejected change requests

  • Question 420:

    Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

    A. Scope plan

    B. Product scope

    C. Scope management plan

    D. Scope baseline

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.