  • Question 31:

    A change requests can occur due to:

    A. An external event such as a change in government regulation.

    B. An error or omission in defining the scope of the product.

    C. An error or omission in defining the scope of the project.

    D. all of the above

  • Question 32:

    At which stage, stakeholders have the maximum influence on a project?

    A. Initial stage

    B. Closing stage

    C. Execution stage

    D. None of the above

  • Question 33:

    An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:

    A. A milestone

    B. A hammock

    C. A dummy activity

    D. a and c

  • Question 34:

    A Project Scope Management includes :

    A. Initiation

    B. Project Plan Execution

    C. Overall Change Control

    D. Report Performance

  • Question 35:

    Which of the following is not a part of the Earned Value calculations?

    A. Unknown Unknowns

    B. Project Budget

    C. Known Unknowns

    D. Amount of work completed

  • Question 36:

    What is the purpose of the WBS?

    A. To show which work elements have been assigned to organizational units.

    B. To ensure that all work within a project is identified and defined within a common framework.

    C. To show the organizational structure of a program.

    D. all of the above

  • Question 37:

    In an optimal organization structure, the project manager is:

    A. Functional

    B. Weak matrix

    C. Piojectized

    D. Dedicated project team

  • Question 38:

    A major assumption of all network scheduling methods is that the activity duration must be .

    A. Statistically dependent

    B. Variance distributed

    C. Statistically independent

    D. Deterministic

  • Question 39:

    Which of the following is not a part of the project cost baseline but is included in the project budget?

    A. Management Contingency Reserve

    B. Management Overheads

    C. Project Management Planing

    D. Activity Cost Contingency Reserve

  • Question 40:

    Which of the following is not a tool or technique for a Source Selection?

    A. Contract negotiation

    B. Weighting system

    C. Payment system

    D. Screening system

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.