PMI CAPM CA0-001 Questions & Answers

  • Question 41:

    Which of the following is ensuring that all features and functions are included in a product or service

    A. Project scope

    B. Project verification

    C. Project control

    D. Product scope

  • Question 42:

    Project risk is defined as the cumulative effect of chances of which will adversely affect project objectives.

    A. Likely events

    B. Complex activities

    C. Complex schedules

    D. Uncertain occurrences

  • Question 43:

    Which of the following is NOT an example of a type of schedule report?

    A. Gantt chart

    B. Milestone chart

    C. fishbone diagram

    D. network diagram

  • Question 44:

    A Change Control Board should be ?

    A. flexible

    B. Include the project manager

    C. appropriate authority

    D. al1 of the above

  • Question 45:

    What involves determining what quantities are to be used to perform project activities.

    A. Resource planning

    B. Estimate Costs

    C. Determine Budget

    D. Control Costs

  • Question 46:

    Which of the following is an output of a Verify Scope process?

    A. Formal acceptance

    B. WBStemplate

    C. SOW acceptance

    D. Rework

  • Question 47:

    With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is .

    A. 30.0

    B. 22.5

    C. 25.0

    D. 27.5

  • Question 48:

    You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year?

    A. $600

    B. $1200

    C. $3000

    D. $100

  • Question 49:

    Analogous Estimate Costs is .

    A. Generally Accurate

    B. Generally less accurate

    C. Bottom-up estimating

    D. None

  • Question 50:

    Adjusting Leads and Lags is a technique for:

    A. Develop Schedule

    B. Estimate Activity Durations

    C. Estimate Activity Resources

    D. Sequence Activities

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.