A Project Manager is at the project kick-off meeting. He confidently states the vision and mission for the project. This PM is exhibiting the following leadership style:
A. Hierarchal
B. Authoritarian
C. Charismatic
D. Associative
Which of the following is a common characteristic of most project life cycle descriptions?
A. Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.
B. The probability of successfully completing the project is highest at the start of the project.
C. Stakeholders have the most influence on the final characteristics of the product at the end of the project.
D. a and b
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?
A. -50%
B. 50%
C. 40%
D. 20%
Which of the following tools and techniques are commonly used in a Define Scope Process?
A. Product analysis
B. Expert Judgment
C. Alternative Identification
D. All of the above
Which of the following relationship is used in the Arrow Diagramming Method [ADM] :
A. Start-to-Finish
B. Finish-to-Start
C. Start-to-Start
D. Finish-to-Finish
When should a project manager be assigned to a project?
A. As early in the project as feasible.
B. Preferably before much project planning has been done.
C. At least prior to the start of project plan execution.
D. All of the above.
A project plan is:
A. A formal, approved document used to guide both project execution and project control.
B. A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.
C. A narrative description of products or services to be supplie
D. A document describing the organizational breakdown structure of the company.
The scope management provides:
A. A basis for future decisions about the project.
B. A baseline to accomplish verification measures.
C. A baseline to evaluate potential scope changes.
D. All of the above.
Another term for top down estimating is:.
A. Analogous estimating
B. Life-cycle costing
C. Parametric modeling
D. Bottom up estimating
A Reserve Analysis is a technique for:
A. Estimate Activity Durations
B. Estimate Activity Resources
C. Sequence Activities
D. Define Activities
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.