PMI PMI Certifications CA0-001 Questions & Answers

  • Question 371:

    What quality control tool graphically represents how various elements of a system interrelate?

    A. Control chart

    B. Flowchart

    C. Run chart

    D. Pareto chart

  • Question 372:

    What is the status of the project whose data is shown in the following S-curve?

    A. Under budget and ahead of schedule

    B. Over budget and behind schedule

    C. Over budget and ahead of schedule

    D. Under budget and behind schedule

  • Question 373:

    If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be the cost performance index (CPI)?

    A. 0.66

    B. 0.8

    C. 1.25

    D. 1.5

  • Question 374:

    Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of what process?

    A. Perform Quality Control

    B. Perform Quality Assurance

    C. Quality Planning

    D. Performance Reporting

  • Question 375:

    What does a SPI value greater than 1.0 indicate?

    A. More work was completed than planned

    B. Less work was completed than planned

    C. Cost overrun for completed work has occurred

    D. Cost underrun for completed work has occurred

  • Question 376:

    Total funding requirements and periodic funding requirements are derived from:

    A. funding limit reconciliation

    B. scope baseline

    C. activity cost estimates.

    D. cost baseline.

  • Question 377:

    Given the following values, what is the calculated expected activity cost (CE) when using PERT?

    CO = $7,000 CM = $10,500 CP = $11,000

    A. $ 4,750

    B. $ 9,500

    C. $10,000

    D. $11,500

  • Question 378:

    What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

    A. $115

    B. $138

    C. $140

    D. $165

  • Question 379:

    Which of the following equations is used to calculate schedule variance?

    A. EV/PV

    B. PV/EV

    C. EV-PV

    D. PV-EV

  • Question 380:

    Which tool and technique uses a statistical relationship between historical data and other variables to calculate estimates?

    A. Analogous estimating

    B. Three-point estimates

    C. Parametric estimating

    D. Bottom-up estimating

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.