  • Question 351:

    Which tools or techniques will the project manager use for developing the project team?

    A. Negotiation

    B. Roles and responsibilities

    C. Recognition and rewards

    D. Prizing and promoting

  • Question 352:

    When managing a project team, what helps to reduce the amount of conflict?

    A. Clear role definition

    B. Negotiation

    C. Risk response planning

    D. Team member replacement

  • Question 353:

    Which of the following describes the purpose of the quality control process?

    A. To identify quality requirements of the project

    B. To identify ineffective processes and eliminate them

    C. To assess performance and recommend necessary changes

    D. To ensure quality standards are used

  • Question 354:

    What is an objective of the Developing Project Team Process?

    A. Feelings of trust and improved cohesiveness

    B. Ground rules for interaction

    C. Enhanced resource availability

    D. Functional managers become more involved.

  • Question 355:

    In which tool and technique is it possible to find a correlation between dependent and independent variables?

    A. Fishbone diagram

    B. Control chart

    C. Run chart

    D. Scatter diagram

  • Question 356:

    A project manager arranges for project specific training for the new team members. Under which category does this cost fall?

    A. Appraisal

    B. Internal failure

    C. External failure

    D. Prevention

  • Question 357:

    What tool and technique includes all costs incurred over the life of a product by investment in preventing nonconformance to requirements?

    A. Cost of quality

    B. Measure of design

    C. Statistical control

    D. Systematic analysis

  • Question 358:

    In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entire process, the goal is 10 and the standard deviation is 1. For this data set, it is correct to say that the process:

    A. is under control.

    B. is out of control.

    C. has an increasing trend.

    D. has a decreasing trend.

  • Question 359:

    What is a cost of nonconformance?

    A. Rework

    B. Inspections

    C. Training

    D. Testing

  • Question 360:

    What is included in a control chart?

    A. Baseline

    B. Planned value

    C. Upper specification limit

    D. Expenditure

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.