What is a technique used in the performance reporting process?
A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings
Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?
A. Risk response planning
B. Manage stakeholders
C. Scope definition
D. Performance reporting
Which of the following is contained within the communications management plan?
A. An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors
Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A. Project Risk Management
B. Project Integration Management
C. Project Communications Management
D. Project Quality Management
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
A. Risk response planning
B. Risk monitoring and control
C. Performance reporting
D. Manage stakeholders
Which of the following involves making information available to project stakeholders in a timely manner?
A. Contract management
B. Performance reporting
C. Project status reports
D. Information distribution
Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A. Project Integration Management
B. Project Communications Management
C. Project Information Management System (PIMS)
D. Project Scope Management
Placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team is called which of the following?
A. Team training
B. Co-location
C. Team location
D. Organization training
Emphasizing areas of agreement rather than areas of difference is part which of the following conflict management techniques?
A. Smoothing
B. Compromising
C. Avoiding
D. Forcing
In which of the following team development stages does the team begin to work together, develop trust, and adjust to the work habits and behavior?
A. Norming
B. Forming
C. Storming
D. Performing
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.