There are seven members on the project team not counting the project manager and the sponsor. How many communication channels are there?
A. 21
B. 28
C. 36
D. 42
ABC project is at risk for failing to achieve a major project objective due to unresolved stakeholder issues. Team member morale is low. Who is primarily responsible for the project being at risk?
A. Team members who have low morale
B. Sponsor who is not actively supporting the project
C. Project manager who is responsible for managing stakeholder expectations
D. Stakeholders who have unrealistic expectations
A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month.
Which tool or technique is used in this case?
A. Expert judgment
B. Quality assurance
C. Quality control
D. Variance analysis
When using the Delphi technique for gathering information, what forecasting method is being used?
A. Time series method
B. Casual method
C. Econometric method
D. Judgmental method
Which of the following is one of the key components of the basic communications model?
A. Push
B. Decode
C. Pull
D. Duration
Which of the following is a tool or technique for distribute information?
A. Project management plan
B. Report performance
C. Communications requirements analysis
D. Communication methods
Which of the following is a tool and technique to the Manage Stakeholder Expectations process?
A. Issue log
B. Change register
C. Stakeholder register
D. Interpersonal skills
Stakeholder analysis identifies what information and relates it to the purpose of the project?
A. Requirements, influence, and functional department
B. Interest, requirements, and functional role
C. Requirements, expectations, and influence
D. Interest, expectations, and influence
What is the number of stakeholders, if the project has 28 potential communication channels?
A. 7
B. 8
C. 14
D. 16
What information does the stakeholder register contain?
A. Communication model
B. Identification information
C. Communication method
D. Identification plan
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.