PMI PMI Certifications CA0-001 Questions & Answers

  • Question 261:

    Which of the following is one of the tools and techniques for the Define Activities process?

    A. Rolling wave planning

    B. Dependency determination

    C. Schedule network template

    D. Applying leads and lags

  • Question 262:

    Which of the following is a tool and technique to develop the schedule?

    A. What-if scenario analysis

    B. Benchmarking

    C. Variance analysis

    D. SWOT analysis

  • Question 263:

    During the initial stages of the project, what do activity attributes include?

    A. Activity name, dependencies, assumptions

    B. Activity ID, WBS ID, activity name

    C. Activity ID, assumptions, constraints

    D. Activity name, WBS ID, activity description

  • Question 264:

    Which of the following is an output of the Estimate Activity Resources process?

    A. Alternative analysis

    B. Bottom-up estimating

    C. Resource breakdown structure

    D. Enterprise environmental factors

  • Question 265:

    In the precedence diagramming method, which of the following is a logical relationship for the activities?

    A. Finish-to-start

    B. Applying leads and lags

    C. Activity-on-node

    D. Dependency determination

  • Question 266:

    Which of the following techniques uses historical information to estimate the activity duration?

    A. Three-point estimating

    B. Organizational process asset

    C. Analogous estimating

    D. Reserve analysis

  • Question 267:

    What is a specific advantage of analogous estimating in comparison with other cost estimate techniques?

    A. Uses contingency reserves

    B. Less costly and time consuming

    C. Can be applied to segments of work

    D. More accurate

  • Question 268:

    Which of these are logical dependencies in a precedence diagram method?

    A. End-to-end

    B. Finish-to-end

    C. Start-to-end

    D. Start-to-start

  • Question 269:

    In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

    A. 90 days

    B. 100 days

    C. 110 days

    D. 660 days

  • Question 270:

    Which schedule format usually shows both the project network logic and the project's critical path schedule activities with activity date information?

    A. Schedule table

    B. Schedule network diagram

    C. Bar chart

    D. Milestone chart

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.