  • Question 141:

    You are project manager of a project, which of the following is not your responsibility?

    A. Quality in the organization

    B. Acquiring HR resources for the project team

    C. Overall responsibility for risk on the project

    D. Al1 of the above

  • Question 142:

    PMI discusses procurement focusing on the relationship.

    A. Buyer or seller

    B. Vendor or seller

    C. Purchasing

    D. Sellino

  • Question 143:

    Administrative closure is the process that .

    A. Closes all activities pertaining to a specific project

    B. Collects user acceptance of the project product or service

    C. Includes all the activities needed to validate the project products and services

    D. Al1 of the above

  • Question 144:

    Which of the following activities is not part of Plan Risk Management?

    A. Updating risk register

    B. Determining risk roles and responsibilities

    C. Identifying risk categories

    D. Developing a risk management plan

  • Question 145:

    is providing detailed plans for tasks that are about to start in the near future using the most current information and revisiting future activities when they near their starting dates.

    A. Rolling wave planning

    B. Progressive elaboration

    C. Milestone detail planning

    D. Expert judgment

  • Question 146:

    Which of the following is conflict resolution technique?

    A. Compromise

    B. Smoothing

    C. Foimal

    D. Coercive

  • Question 147:

    Which of the following is NOT an input of close project process?

    A. Project management plan

    B. Contract documentation

    C. Deliverables

    D. WBS

  • Question 148:

    Which of the following statement is true about project charter?

    A. Provides a high level definition of the effort and its stakeholders

    B. Announces who is the project engineer

    C. Tells the newspapers and media when the project will end

    D. Announces who is the project sponsor

  • Question 149:

    Assumptions in the project plan should be .

    A. Written down

    B. Understandable

    C. Not understandable

    D. No need to write

  • Question 150:

    Who applies project selection methods to decide whether to accept or reject a project?

    A. Project sponsor

    B. Project team

    C. Project manager

    D. Senior Management

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.