You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in .
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements
Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
A. Parametric estimating
B. Funding limit reconciliation
C. Reserves analysis
D. None of the above
Which is not part of Project Plan?
A. Project Scope Management Plan
B. Schedule Management Plan
C. Cost Management Plan
D. Project Charter
Which of the following is the most important task of the project manager during the Execution and Control phase?
A. Information management
B. Maintain scope statement
C. Maintain Charter
D. Maintain Closing document
Which statement is true about Bottom-up estimating?
A. Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.
B. Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.
C. Using project characteristics (or parameters) in a mathematical model to predict costs.
D. Cost of quality can also be used to prepare the schedule activity cost estimate.
From whom do you need to gain the formal acceptance at project closure?
A. The customer
B. The qualify director
C. Project management office
D. Project manager
At what point in a project do you have the highest probability that it will fail?
A. The beginning of the project
B. ^ust before the end of the project
C. QA Phase
D. Execution phase
You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?
A. Pi'ojectized
B. Strong Matrix
C. Weak Matrix
D. Functional
If a project with a SPI of 1.8, what you tell?
A. The project is running ahead of the schedule
B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None
The work breakdown structure is .
A. Used to break down the project into manageable pieces
B. Set and does not change throughout the project
C. Needed as part of the project charter
D. [Needed as part of the project scope statement
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.