  • Question 131:

    Which of the following subsidiary plan contains the quality objectives for the project?

    A. Quality baseline

    B. Quality management plan

    C. Process improvement plan

    D. QA checklist

  • Question 132:

    You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?

    A. Save the old versions

    B. No need to save old version

    C. Scrap the old version

    D. Old version is not required

  • Question 133:

    Which of the following is not a form a leadership power?

    A. Compromise

    B. Smoothing

    C. Foimal

    D. Coercive

  • Question 134:

    is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.

    A. Procurement Management

    B. Planning Management

    C. Scope Management

    D. Control Management

  • Question 135:

    The project baseline is .

    A. Original plans plus the approved changes

    B. Important in the project initiation phase

    C. Initial estimates for tasks and resource utilization

    D. Original plans and the approved major changes

  • Question 136:

    The intent of the risk management process group is to .

    A. Increase the probability of positive outcomes in the project

    B. Announce project risks

    C. Not consider risks affecting the company

    D. Announce project deliverables

  • Question 137:

    ISO Stands for .

    A. International Organization for Standardization

    B. International Standardized Organization

    C. 'n Standardized Organization

    D. Indiana Standardized Organization

  • Question 138:

    Which one of the following is not an output of contract closure?

    A. c'ose contracts

    B. Lessons learned documentation

    C. Deliverable acceptance

    D. Scope statement

  • Question 139:

    You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow's hierarchy of needs, what needs level he most likely is at?

    A. Social need

    B. Physical need

    C. Safety and security

    D. Security

  • Question 140:

    Project success can be achieved only if:

    A. There is a clear link between the project deliverables and the business strategy.

    B. The project sponsor leads the initiatives.

    C. The project manager is an expert in managing resources.

    D. Team members like project manager.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.