Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
A. The Delphi technique
B. Nominal group technique
C. Affinity diagram
D. Brainstorming
Which defines the portion of work included in a contract for items being purchased or acquired?
A. Procurement management plan
B. Evaluation criteria
C. Work breakdown structure
D. Procurement statement of work
To which process is work performance information an input?
A. Administer Procurements
B. Direct and Manage Project Execution
C. Create WBS
D. Perform Qualitative Risk Analysis
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
A. Decomposition
B. Benchmarking
C. Inspection
D. Checklist analysis
Which of the following processes are part of the Project Integration Management Knowledge Area?
A. Develop Project Management Plan, Collect Requirements, Create WBS
B. Develop Project Management Plan, Control Scope, Develop Schedule
C. Develop Project Charter, Define Scope, Estimate Costs
D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase
A procurement management plan is a subsidiary of which other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
A. Customer request
B. Market demand
C. Technological advance
D. Strategic opportunity
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
A. To the project management plan.
B. To the risk register.
C. In the scope verification processes.
D. And their impact to the project in terms of time, cost, and risk.
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
A. Perform Qualitative Risk Analysis
B. Perform Quantitative Risk Analysis
C. Plan Risk Management
D. Plan Risk Responses
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
A. The influence of the stakeholders increases, the cost of changes increases.
B. The influence of the stakeholders decreases, the cost of changes increases.
C. The influence of the stakeholders increases, the cost of changes decreases.
D. The influence of the stakeholders decreases, the cost of changes decreases.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.