  • Question 301:

    Which type of managers do composite organizations involve?

    A. Functional managers and manager of project managers

    B. Functional managers only

    C. Project managers only

    D. Technical managers and project managers

  • Question 302:

    Assigned risk ratings are based upon:

    A. Root cause analysis.

    B. Risk probability and impact assessment.

    C. Expert judgment.

    D. Revised stakeholders' tolerances.

  • Question 303:

    Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

    A. Initiating

    B. Monitoring and Controlling

    C. Planning

    D. Closing

  • Question 304:

    Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

    A. Collect Requirements

    B. Direct and Manage Project Execution

    C. Monitor and Control Project Work

    D. Develop Project Management Plan

  • Question 305:

    What is one of the objectives of Project Risk Management?

    A. Decrease the probability and impact of an event on project objectives.

    B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

    C. Increase the probability and impact of positive events.

    D. Removal of project risk.

  • Question 306:

    Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

    A. Identify Risks

    B. Perform Qualitative Risk Analysis

    C. Plan Risk Management

    D. Perform Quantitative Risk Analysis

  • Question 307:

    Which of the following involves making information available to project stakeholders in a timely manner?

    A. Plan Communications

    B. Performance reporting

    C. Project status reports

    D. Distribute Information

  • Question 308:

    Which Process Group typically consumes the bulk of a project's budget?

    A. Monitoring and Controlling

    B. Executing

    C. Planning

    D. Initiating

  • Question 309:

    Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

    A. Develop Project Management Plan

    B. Develop Project Charter

    C. Direct and Manage Project Execution

    D. Collect Requirements

  • Question 310:

    When is a project finished?

    A. After verbal acceptance of the customer or sponsor

    B. After lessons learned have been documented in contract closure

    C. When the project objectives have been met

    D. After resources have been released

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.