  • Question 271:

    The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

    A. US$158,700

    B. US$172,500

    C. US$187,500

    D. US$245,600

  • Question 272:

    Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

    A. Control chart

    B. Earned value

    C. Variance

    D. Trend

  • Question 273:

    Which is one of the major outputs of Sequence Activities?

    A. Responsibility assignment matrix (RAM)

    B. Work breakdown structure (WBS) update

    C. Project schedule network diagram

    D. Mandatory dependencies list

  • Question 274:

    An output of the Create WBS process is:

    A. Scope baseline.

    B. Project scope statement.

    C. Organizational process assets.

    D. Requirements traceability matrix.

  • Question 275:

    Change requests are an output from which Project Integration Management process?

    A. Direct and Manage Project Execution

    B. Develop Project Management Plan

    C. Close Project

    D. Develop Project Charter

  • Question 276:

    Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

    A. Estimate Costs

    B. Estimate Activity Resources

    C. Control Costs

    D. Determine Budget

  • Question 277:

    When can pre-assignment of project team members occur?

    A. When the project uses capital expenditures

    B. When the required staff can be acquired from outside sources

    C. When the project would be ignored due to travel expenses

    D. When the project is the result of specific people being promised as part of a competitive proposal

  • Question 278:

    What type of project structure is a hierarchically organized depiction of the resources by type?

    A. Organizational breakdown structure (OBS)

    B. Resource breakdown structure (RBS)

    C. Work breakdown structure (WBS)

    D. Project breakdown structure (PBS)

  • Question 279:

    At which point of the project is the uncertainty the highest and the risk of failing the greatest?

    A. Final phase of the project

    B. Start of the project

    C. End of the project

    D. Midpoint of the project

  • Question 280:

    Cost baseline is an output of which of the following processes?

    A. Control Costs

    B. Determine Budget

    C. Estimate Costs

    D. Estimate Activity Resources

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.