Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
A. Bottom-up
B. Three-point
C. Parametric
D. Analogous
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
A. Control Schedule
B. Define Activities
C. Develop Schedule
D. Estimate Activity Resources
Perform Quality Control is accomplished by:
A. Identifying quality standards that are relevant to the project and determining how to satisfy them.
B. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.
C. Ensuring that the entire project team has been adequately trained in quality assurance processes.
D. Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
A. Critical path method
B. Variance analysis
C. Schedule compression
D. Schedule comparison bar charts
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A. Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline
What type of reward can hurt team cohesiveness?
A. Sole-sum
B. Win-lose
C. Lose-win
D. Partial-sum
What is the name of a graphic display of project team members and their reporting relationships?
A. Role dependencies chart
B. Reporting flow diagram
C. Project organization chart
D. Project team structure diagram
Which tool is used to develop technical details within the project management plan?
A. Expert judgment
B. Project management methodology
C. Project management information system (PMIS)
D. Project selection methods
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
A. -700
B. -200
C. 200
D. 500
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.