Q4 Single choice

A PMO professional identified that the strategic project's stakeholders are dissatisfied with the visibility of project progress, citing a lack of visibility into key performance indicators (KPIs) and communication. The project manager ensured that the current PMO reporting process and requirements are being followed.

Which action should the PMO professional take?