PMI-RMP Web TestEngine demo

Exit VCEDump PMI-RMP PMI Risk Management Professional (PMI-RMP)
Question 82 of 100
0% complete
Q82 Single choice

A risk manager completed risk response planning for a project that is currently in the execution phase.
During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?