Question 38 of 100
0% complete
Q38 Single choice

A project manager wants to represent the distribution of uncertainty around a risk model element.
However, good data on the variability, of the risk model element has not been collected, and only contains minimum and maximum values.

What curve should the project manager use to represent the distribution?