Question 76 of 100
0% complete
Q76 Single choice

Shelly is the project manager of the BUF project for her company. In this project Shelly needs to establish some rules to reduce the influence of risk bias during the qualitative risk analysis process.

What method can Shelly take to best reduce the influence of risk bias?