Question 40 of 68
0% complete
Q40 Single choice

Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B's program manager has just advised that program
B has been closed.

What should program A's program manager update and review first with the stakeholders?