Question 37 of 68
0% complete
Q37 Single choice

You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training.
The cost of the training in this instance is known as which one of the following?