Q34 Single choice

You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays.

What principle should you share with these project managers that counterattack the concept of padding activities with additional time?