Exam Details

  • Exam Code
    :PSPO-I
  • Exam Name
    :Professional Scrum Product Owner I
  • Certification
    :Scrum Certifications
  • Vendor
    :Scrum
  • Total Questions
    :161 Q&As
  • Last Updated
    :May 11, 2025

Scrum Scrum Certifications PSPO-I Questions & Answers

  • Question 61:

    Who determines how work is performed during the Sprint?

    (choose the best answer)

    A. The Scrum Master.

    B. The Scrum Team.

    C. Team manager.

    D. The Developers

    E. Subject matter experts.

  • Question 62:

    What is the accountability of the Product Owner during Sprint 0?

    (choose the best answer)

    A. Determine the composition of the Scrum Team to meet the release plan.

    B. There is no such thing as Sprint 0.

    C. Create the overall release plan to ensure that organizational goals are met.

    D. Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

    E. Gathering, eliciting, and analyzing the requirements to build the Product Backlog.

  • Question 63:

    What three things might a Scrum Product Owner focus on to ensure the product delivers value?

    (choose the best three answers)

    A. How much of the functionality of the product is being used.

    B. Direct customer feedback.

    C. How quickly or easily the product can be absorbed and used by its customers.

    D. Velocity is increasing over time.

    E. Minimizing changes to project scope.

  • Question 64:

    True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.

    A. True

    B. False

  • Question 65:

    Who is accountable for managing the progress of work during a Sprint?

    (choose the best answer)

    A. The Developers.

    B. The most junior member of the team.

    C. The Scrum Master.

    D. The Product Owner.

  • Question 66:

    All Scrum artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensure that the Product Backlog is transparent?

    (choose the best two answers)

    A. The Product Backlog is ordered.

    B. The Product Backlog is available to all stakeholders.

    C. Each Product Backlog item has a MoSCoW priority.

    D. The Product Backlog only has work for the next 2 Sprints.

    E. The Product Backlog is managed using a web-based tool.

  • Question 67:

    When does a Sprint conclude?

    (choose the best answer)

    A. When all the tasks are completed by the Developers.

    B. When the Sprint Retrospective is complete.

    C. When all Product Backlog items meet their Definition of Done.

    D. When the Product Owner decides enough has been delivered to meet the Sprint Goal.

  • Question 68:

    True or False: Scrum has a role called "Project Manager".

    A. True

    B. False

  • Question 69:

    What are the two responsibilities of testers in a Scrum Team?

    (choose the best two answers)

    A. Tracking quality metrics.

    B. Scrum has no "tester" role.

    C. Verifying the work of programmers.

    D. The Developers are responsible for quality.

    E. Finding bugs.

  • Question 70:

    True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.

    A. True

    B. False

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSPO-I exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.