Scrum Scrum Certifications PSPO-I Questions & Answers

  • Question 141:

    When can Developers cancel a Sprint?

    (choose the best answer)

    A. When functional expectations are not well understood.

    B. When the selected Product Backlog items for the Sprint become unachievable.

    C. They cannot. Only Product Owners can cancel Sprints.

    D. When the Product Owner is absent too often.

    E. When a technical dependency cannot be resolved.

  • Question 142:

    Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

    (choose the best answer)

    A. The Project Manager.

    B. The Product Owner.

    C. The Scrum Master.

    D. The Scrum Team.

    E. All of the above.

  • Question 143:

    True or False: Product Owners must specify complete acceptance criteria for a Product

    Backlog item before the Developers can select the item in Sprint Planning.

    A. True

    B. False

  • Question 144:

    True or False: Multiple Scrum Teams working on the same product must have the same Sprint start date.

    A. True

    B. False

  • Question 145:

    Which statement best describes the Sprint Review?

    (choose the best answer)

    A. It is a mechanism to control the Developers activities during a Sprint.

    B. It is used to congratulate the Developers if they complete their forecast or to punish the Developers if they fail to meet their forecast.

    C. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

    D. It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

  • Question 146:

    During a Sprint Retrospective, the Developers propose moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master to recommend?

    (choose the best two answers)

    A. Have the Developers vote.

    B. Acknowledge and support the self-managing team's decision.

    C. Coach the team on why the Daily Scrum is important as an opportunity to update the plan.

    D. Consider the request and decide on which days the Daily Scrum should occur.

    E. Learn why the Developers want this and work with them to improve the outcome of the Daily Scrum.

  • Question 147:

    During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate?

    (choose the best answer)

    A. The Scrum Team may add the items to the Sprint Backlog for the next Sprint.

    B. The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are running smoothly.

    C. The Scrum Team should choose at least one high priority process improvement to place in the Product Backlog.

    D. The Scrum Master selects the most important process improvement and places it in the Sprint Backlog

  • Question 148:

    Which statement best describes Scrum?

    (choose the best answer)

    A. A defined and predictive process that conforms to the principles of Scientific Management.

    B. A complete methodology that defines how to develop software.

    C. A framework to generate value through adaptive solutions for complex problems.

    D. A cookbook that defines best practices for software development.

  • Question 149:

    Who starts the Daily Scrum?

    (choose the best answer)

    A. The Scrum Master. This ensures that the Developers have the event, and it stays within the timebox.

    B. The person coming in last. This encourages people to be on time and helps to stay within the timebox.

    C. The Product Owner.

    D. Whoever the Developers decide should start.

    E. The person who has the token.

  • Question 150:

    When is the Sprint Backlog created?

    (choose the best answer)

    A. Prior to Sprint Planning.

    B. During refinement.

    C. During the Sprint Retrospective.

    D. During Sprint Planning.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSPO-I exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.