How should multiple Scrum Teams, working from the same Product Backlog, select the Product Backlog items their teams plan to work on?
A. The Product Owner will present the work and the Development Teams will select the items they will work on.
B. The Product Owner creates separate Product Backlogs for each Development Team.
C. Each Scrum Team would select an equal number of items.
D. The Product Owner assigns the work to each team.
E. The Scrum Team with the highest productivity will select the items first.
What would be the responsibilities of a self-organizing Development Team?
A. Update stakeholders on the daily progress and keep the burn-down chart updated.
B. Select the Product Backlog items for the Sprint and do the work planned in the Sprint Backlog.
C. Writing User Stories and reordering the Product Backlog.
D. Deciding on the value of the product features and value estimations.
What should a Development Team do with non-functional requirements?
A. Ensure they are addressed in every Increment.
B. Assign them to the technical leads on the team.
C. They will be addressed in the Integration Sprints.
D. Add them to a separate non-functional requirements list.
What should a Development Team do if they don't understand a functional requirement?
A. Request a specialist to be added to the Development Team.
B. Move the item to a future Sprint.
C. Complete as much as possible and add the remaining work as a new Product Backlog item.
D. Work with the Product Owner to determine what is possible and acceptable.
What should a Development Team do if it realizes it has selected too much work after starting the Sprint?
A. Modify the definition of "Done" to ensure all Product Backlog items can be done by the end of the Sprint.
B. Work with the Product Owner to remove some work or Product Backlog items as soon as possible.
C. Add additional team members to handle the extra work.
D. Continue working and update the Product Owner at the Sprint Review.
What Development Team structure is best suited to produce integrated increments?
A. Every Development Team has the abilities to develop functionality from beginning to end throughout all technical layers.
B. Each Development Team specializes in one technical layer of the system (e.g. GUI, database, middle tier, interfaces).
Who determines how to do the work during the Sprint?
A. The Scrum Master.
B. The Technical Architects.
C. The Development Team.
D. The Team Leads.
E. The engineering director.
What is the recommended size for a Development Team (within the Scrum Team)?
A. 3 to 9
B. Minimal 5
C. 7 plus or minus 2
D. 9
Who should be present to review and adjust the selected Sprint work if the Development Team determines that it will not be able to finish the complete forecast?
A. The stakeholders and Scrum Master.
B. The Product Owner and the Development Team.
C. The Development Team and Project Manager.
D. The Scrum Master, the Business Analyst and the Development Team.
According to Scrum theory, how should a group of fifty people be divided into multiple Development Teams?
A. Allow the team leads to divide and select teams.
B. Understanding the product, the product vision and the Scrum framework, the group self-organizes into teams.
C. Create a skills matrix, identify role levels, and years of experience to assign people to teams.
D. The teams will rotate members every Sprint to spread knowledge.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSM-II exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.