  • Question 381:

    Which of the following is FALSE?

    A. Manage risks is a PRINCE2 principle
    B. Manage by exception is a PRINCE2 principle
    C. Focus on products is a PRINCE2 principle
    D. Tailor to suit the project environment is a PRINCE2 principle

  • Question 382:

    How should the 'managing a stage boundary' process be used towards the end of a project's final delivery stage?

    A. To plan the activities of the 'closing a project process
    B. To implement any exception plan requests from the project board
    C. To create a benefits management approach for corporate, programme management or the customer
    D. To review an issue received from a team manager

  • Question 383:

    Which of the following is a prioritized list of measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders?

    A. Acceptance criteria
    B. Quality criteria and related tolerance
    C. Project Product Description
    D. Product Status Account

  • Question 384:

    Which does a Project Manager produce to define and control the work to be done?

    A. Configuration Item Record
    B. Stage scope tolerance
    C. Team Plan
    D. Work Package

  • Question 385:

    In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

    A. Product Description
    B. Team Plan
    C. Work Package
    D. Stage Plan

  • Question 386:

    Which statement about stages is true?

    A. Management stages should be of the same duration
    B. The use of technical stages is mandatory
    C. The use of management stages is mandatory
    D. Management stages are driven by specialist teams

  • Question 387:

    What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?

    A. Event-driven
    B. Exception based
    C. Time-driven
    D. Ad-hoc

  • Question 388:

    Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

    A. Corporate group
    B. Project Board
    C. Project Assurance
    D. Executive

  • Question 389:

    Which is a purpose of a Lessons Report?

    A. Improve the project management method for future projects
    B. Detail open issues and risks that need to be managed after the project has closed
    C. Compare the actual performance of the final stage against its plan
    D. Provide a summary of the benefits realized during the project

  • Question 390:

    Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

    A. Benefits
    B. Quality
    C. Risk
    D. Scope

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.