PRINCE2 PRINCE2-FOUNDATION Online Questions & Answers

  • Question 331:

    What is the collective name for individuals or groups who may be affected by a project?

    A. Customers
    B. Project Support
    C. Stakeholders
    D. Team members

  • Question 332:

    Which of the following is a specific objective of the Managing Product Delivery process?

    A. The project management team is focused on delivery within the tolerances laid down
    B. The Business Case is kept under review
    C. Attention is focused on delivery of the stage's products
    D. Team Managers, team members and suppliers are clear as to what is to be produced and what is the expected effort, cost or timescale

  • Question 333:

    Which is a minimum requirement for applying the 'quality' theme?

    A. Completed products must be reviewed using the PRINCE2 quality review technique
    B. Independent reviews of the project must be carried out throughout its lifecycle
    C. Approval records must be kept to show formal approval has been given
    D. Quality criteria for products must be specified in their product descriptions

  • Question 334:

    Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

    A. Capture
    B. Examine
    C. Propose
    D. Decide

  • Question 335:

    Which of the following is a prioritized list of measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders?

    A. Acceptance criteria
    B. Quality criteria and tolerances
    C. Quality and approval records
    D. Customer's quality expectations

  • Question 336:

    A project being output oriented supports which PRINCE2 principle?

    A. Focus on products
    B. Defined roles and responsibilities
    C. Manage by stages
    D. Continued business justification

  • Question 337:

    What is the name given to an individual who is responsible for the management, monitoring and control of all aspects of a particular risk assigned to them?

    A. Risk Actionee
    B. Risk Coordinator
    C. Project Risk Manager
    D. Risk Owner

  • Question 338:

    Which is a true statement about time-driven controls?

    A. Time-driven controls are used for monitoring the progress of Work Packages and management stages
    B. Time-driven controls take place when specific events happen
    C. Time-driven controls are produced at the end of a stage
    D. An Exception Report is a time-driven control

  • Question 339:

    According to PRINCE2, as well as holding informal problems/concerns, which product can also be used to record required actions or significant events not caught elsewhere?

    A. Daily Log
    B. Risk Register
    C. Issue Register
    D. Project notebook

  • Question 340:

    Which is NOT a recommended response to a threat?

    A. Avoid
    B. Exploit
    C. Share
    D. Transfer

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.