PRINCE2 PRINCE2-FOUNDATION Online Questions & Answers

  • Question 261:

    Which describes risk probability?

    A. Level of risks which the project can tolerate before escalating to the Project Board
    B. Probable effect on the project delivering its objectives
    C. Timeframe within which the risk may occur
    D. A measure of the likelihood of the risk occurring

  • Question 262:

    Which reason explains why the ‘learn from experience’ principle is important?

    A. The temporary project team may not have delivered similar work
    B. Projects should contribute to the development of staff
    C. It helps to prevent projects duplicating other projects’ objectives
    D. User staff often do not have enough time to participate in project work

  • Question 263:

    What is an objective of the Managing a Stage Boundary process?

    A. Request authorization to start the next stage
    B. Ensure that all threats and opportunities for the current stage have been closed
    C. Make certain that work on products allocated to the team for the next stage is authorized and agreed
    D. Implement actions to resolve tolerance deviations from the Stage Plan

  • Question 264:

    Which of the following products is used after the Starting Up a Project process to capture and maintain information on all of the identified threats and opportunities relating to the project?

    A. Risk Management Strategy
    B. Risk Register
    C. Issue Register
    D. Quality Register

  • Question 265:

    Which PRINCE2 role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?

    A. Team Manager
    B. Project Assurance
    C. Change Authority
    D. Project Manager

  • Question 266:

    Identify the missing word(s) in the following sentence... Change can only be considered in relation to an established [ ? ]

    A. Baseline
    B. Situation
    C. Product
    D. Specification

  • Question 267:

    Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

    A. Project Brief
    B. Project Initiation Documentation
    C. Project mandate
    D. Benefits Review Plan

  • Question 268:

    Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

    A. End stage report
    B. Checkpoint report
    C. Highlight report
    D. Exception report

  • Question 269:

    Which of the following management levels sits outside of the project management team?

    A. Directing
    B. Managing
    C. Corporate or programme management
    D. Delivering

  • Question 270:

    Which plan is optional depending on the complexity of the project?

    A. Project Plan
    B. Exception Plan
    C. Team Plan
    D. Initiation Stage Plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.