  • Question 221:

    Which process provides the Project Board with the information it requires in order to commit resources to the project?

    A. Managing Product Delivery
    B. Initiating a Project
    C. Controlling a Stage
    D. Directinga Project

  • Question 222:

    What factors need to be taken into consideration when identifying the number of management stages required?

    1.

    Where key decisions points need to be

    2.

    The amount of risk within the project

    3.

    The number of technical stages

    4.

    How confident the Project Board and Project Manager are with proceeding

    A. 1,2,3
    B. 1,2,4
    C. 1,3,4
    D. 2,3,4

  • Question 223:

    Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

    A. quality
    B. supplier
    C. risk
    D. product

  • Question 224:

    Which is an objective of the Closing a Project process?

    A. Provision has been made to address any open issues or risks with follow-on action recommendations
    B. Request authorization to start the next stage
    C. Prepare an Exception Plan as directed by the Project Board
    D. Ensure that the planned products are delivered to expectations and within tolerance

  • Question 225:

    There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?

    A. Initiation as the first stage, the remainder of the project as the second stage
    B. Initiation as the first stage, closure activities as the second stage
    C. Procurement as the first stage, design and implementation as the second stage
    D. Pre-project work as the first stage, initiation as the second stage

  • Question 226:

    Which is a definition of management?

    A. Directing the execution of project tasks as agreed for the project
    B. A way of working that characterises a group of people
    C. Being accountable to the business for the success of the project
    D. The party responsible for commissioning the project

  • Question 227:

    Who are allowed to raise an issue?

    A. Only the Project Manager and Team Manager
    B. Anyone with an interest in the project or its outcome
    C. Only the Change Authority
    D. Only members of the project management team

  • Question 228:

    What is a purpose of quality planning?

    A. Provide information from the undertaking of the quality methods
    B. Maintain the quality and approval records stemming from the planned quality checks
    C. To produce the Project Plan with resource information
    D. Identify the means by which quality will be achieved and assessed

  • Question 229:

    On which environment is PRINCE2 based?

    A. Information technology
    B. Customer/supplier
    C. Procurement
    D. Programme

  • Question 230:

    What theme provides all management levels within the project management team with mechanisms for monitoring and control?

    A. Progress
    B. Change
    C. Organization
    D. Quality

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.