Question 1 Single choice

Which statement explains how the `learn from experience' principle is applied in an agile context?

  1. A

    It focuses on the prioritization and decomposition of requirements

  2. B

    It integrates releases within management stages

  3. C

    It is supported by the `inspect and adapt' concept

  4. D

    It provides guidance on mapping PRINCE2 roles to an agile environment

Show answer and explanation

Correct answer: C

Explanation

References:
https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_46

Question 2 Single choice

How is the `tailor to suit the project' principle applied in an agile context?

  1. A

    By flexing what is produced to stay in control and deliver value

  2. B

    By emphasizing tolerances on what is being delivered

  3. C

    By using the Agilometer to assess the project environment

  4. D

    By fitting releases into planned management stages

Show answer and explanation

Correct answer: A

Question 3 Single choice

Which is a key objective of running a workshop?

  1. A

    To make daily progress visible to the delivery team and key stakeholders

  2. B

    To encourage collaboration and create the defined outputs from the event

  3. C

    To communicate decisions to the wider stakeholder community

  4. D

    To make day-to-day decisions on behalf of the delivery team within a sprint

Show answer and explanation

Correct answer: B

Explanation

References:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_166&showNav=true&expandNav=true

Question 4 Single choice

In which area is Agile strongest when blending with PRINCE2?

  1. A

    Product delivery

  2. B

    Project management

  3. C

    Project direction

  4. D

    Product management

Show answer and explanation

Correct answer: A

Explanation

References:
https://hennyportman.wordpress.com/2015/07/01/prince2-agile-in-one-picture/#:~:text=This%20framework%20is%20based%20on,the%20area%20of%20product%20delivery

Question 5 Single choice

Why are team working agreement produced?

  1. A

    To create structure so that the team manager can assess individual performance

  2. B

    To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

  3. C

    To make the team rules visible to the project manager for monitoring purposes

  4. D

    To ensure that the delivery team members comply with company policy

Show answer and explanation

Correct answer: B

Explanation

Reference
https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true

Question 6 Single choice

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  1. A

    1 and 2

  2. B

    2 and 3

  3. C

    3 and 4

  4. D

    1 and 4

Show answer and explanation

Correct answer: D

Explanation

References:
https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_206&showNav=true&expandNav=true

Question 7 Single choice

Which statement explains the PRINCE2 Agile behavior of `exploration'?

  1. A

    It empowers the project management team at the delivery level

  2. B

    It uses the most effective channel to communicate information

  3. C

    It displays the progress rate to everyone using burn-down charts

  4. D

    It seeks out feedback collaboratively from project stakeholders

Show answer and explanation

Correct answer: D

Explanation

References:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_47&showNav=true&expandNav=true

Question 8 Single choice

Which TWO are the purposes of a highlight report?

1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks

  1. A

    1 and 2

  2. B

    2 and 3

  3. C

    3 and 4

  4. D

    1 and 4

Show answer and explanation

Correct answer: C

Explanation

References:
https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_190&showNav=true&expandNav=true#:~:text=A%20highlight%20report%20is%20used,at%20intervals%20defined%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help

Question 9 Single choice

Which is a typical characteristic of `business as usual' work?

  1. A

    It requires a specific dedicated project manager

  2. B

    It is executed by program management

  3. C

    It is delivered by a temporary team

  4. D

    It is delivered by an established team

Show answer and explanation

Correct answer: D

Explanation

References:
https://www.prince2primer.com/prince2-agile-overview-part-1/

Question 10 Single choice

Why is Lean Startup included in the `starting up a project' process in PRINCE2 Agile?

  1. A

    Because it explains how a small company can grow using traditional technologies

  2. B

    Because it is designed to manage projects, delivering products in timeboxes

  3. C

    Because it enables agile to be used in challenging and uncertain situations

  4. D

    Because running a project and setting up a new business are the same

Show answer and explanation

Correct answer: C

Explanation

References:
https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_127&showNav=true&expandNav=true