The most appropriate model for a geographically distributed project team is one in which the team is distributed across:
A. relatively few locations, with each location team comprised of a complete development group developing decoupled subsystems.An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.
What should the agile lead do to ensure the release will be on time for the fair?
A. Reduce the scope of the release to meet the deadline.An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work. What metrics should the team use to measure performance?
A. Lead time, throughput, and due date performanceA legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope. What should the scrum master do?
A. Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scopeAn organization initiates a pilot project to introduce agile methodology for the successful delivery of projects.
What should the project manager do to share this project's knowledge and learning with wider organizational business groups?
A. Invite people from across the organization to attend daily stand upsDuring team meetings, the team often struggles with making decisions about their technical approach. What should be done to improve the quality and timeliness of decisions?
A. Work with the team to improve collaboration by fostering group decision making and conflict resolution techniques.A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed. What should the project manager do to make sure team members are following up on risks?
A. Hold one daily coordination meeting to determine the reason team members are not following up on risks.A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement. Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?
A. Requirements backlog and ready for releaseContinuous attention to_____________ and good design enhances agility.
A. Best architecturesDuring an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance. How should the agile practitioner handle the recommendation?
A. Record the suggestion to be considered for future projects.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.