  • Question 81:

    A project manager has decided to make a scope change in the SOW. Which of the following should the project manager do first in the process?

    A. Discuss with a team lead.
    B. Move to the next step in the process.
    C. Communicate with the project sponsor.
    D. Have a meeting with the human resources department.

  • Question 82:

    During online, collaborative meeting sessions, a project team is consistently in consensus, which is causing a creativity roadblock. Which of the following can the facilitator do to minimize this issue?

    A. Enable chat.
    B. Distribute surveys.
    C. Meet face to face.
    D. Use a whiteboard.

  • Question 83:

    Two project members keep missing recurring meetings due to the meetings taking place when the members are not at work.

    Which of the following types of communication barriers does this describe?

    A. Geographical
    B. Language
    C. Technological
    D. Cultural difference

  • Question 84:

    A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the

    communicated expectations.

    Which of the following tools should the project manager use to validate the functionality?

    A. Project status report
    B. Requirements Traceability Matrix
    C. Detect log
    D. Signed project charter
    E. Work breakdown structure

  • Question 85:

    A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?

    A. Access project artifacts.
    B. Arrange a brainstorming session.
    C. Conduct a kickoff meeting.
    D. Establish communication channels.

  • Question 86:

    A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

    A. Avoid injuries by using robots to perform tasks.
    B. Transfer risk to an insurance company.
    C. Mitigate risk by training the construction workers.
    D. Accept the risks inherent to construction.

  • Question 87:

    Which of the following items must be protected as Pll? (Select TWO).

    A. Job title
    B. Home address
    C. Work phone number
    D. Time zone
    E. Date of birth
    F. Blood type

  • Question 88:

    Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

    A. Maintenance window
    B. Risk assessment
    C. Operational security
    D. Validation check

  • Question 89:

    Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

    A. Send out a survey to the potential end users to gather information about the best functional setup for work productivity.
    B. Provide clear instructions based on personal preference and aesthetics for setup of the work areas.
    C. Explain to team members that the placement of the items is not too important, as long as everything is connected and working.
    D. Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

  • Question 90:

    A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?

    A. Create a new project management plan.
    B. Collect all project meeting minutes.
    C. Perform project scope management.
    D. Review the project charter.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.