  • Question 21:

    A company has several conflicting proposed initiatives. Which of the following is the steering committee responsible for accomplishing?

    A. Collecting customer feedback
    B. Deciding which projects to pursue
    C. Obtaining current deliverable status
    D. Leading application development

  • Question 22:

    During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter.

    Which of the following activities would have most likely avoided this discrepancy?

    A. Validation of deliverables
    B. Closing contracts
    C. Project sign-off
    D. Removing access

  • Question 23:

    A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

    A. Each feature will have a different owner.
    B. The majority of the team can only meet on a weekly basis.
    C. The stakeholders have provided a specific deadline to meet.
    D. Each feature has a specific budget allocation.

  • Question 24:

    A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

    A. The project closeout report
    B. A handover to operations
    C. Phase-gate review documentation
    D. A transition plan

  • Question 25:

    Which of the following scenarios best illustrates how language barriers can negatively impact effective communication within a project team?

    A. A project team is unable to communicate effectively due to a lack of common technical terminology and jargon
    B. A project team refuses to learn foreign languages to cater to remote colleagues
    C. A project team cannot use communication tools due to a lack of IT knowledge
    D. A project team member located in a different time zone fails to access project resources

  • Question 26:

    A project manager is assigned multiple projects and is falling behind in preparing and distributing meeting minutes and action items.

    Which of the following should the project manager do?

    A. Record the meetings for playback.
    B. Ask all team members to take notes.
    C. Hold meetings monthly instead of weekly.
    D. Assign a scribe to prepare the documents.

  • Question 27:

    Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

    A. Real-time surveys/polling
    B. Wiki knowledge base
    C. Spreadsheets
    D. Meetings/face-to-face
    E. Real-time, multi-authoring editing software
    F. Charting/diagramming

  • Question 28:

    For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

    A. Resource plan
    B. Organizational chart
    C. Project charter
    D. RACI chart

  • Question 29:

    A project manager is working with a new team to review a requirement for a new project. The project manager wants to create artifacts that include roles and responsibilities.

    Which of the following artifact types best matches these requirements?

    A. RACI chart
    B. Gantt chart
    C. Burndown chart
    D. Organizational chart

  • Question 30:

    Which of the following IT elements allows developers to leverage existing code to integrate with other software systems?

    A. SaaS
    B. API
    C. Databases
    D. End user applications

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.