Which of the following are characteristics of a project? (Choose two.)
A. Ongoing
B. Temporary
C. Start and finish
D. Achieving a goal
E. Consisting of milestones
F. Restricting the budget
A project manager reviews a new project charter and notices that the project objective is similar to a project that was done in the past. Which of the following actions should the project manager take?
A. Review the existing artifacts and customize accordingly.
B. Utilize the existing artifacts to manage the project.
C. Ask the previous project manager for advice.
D. Notify the sponsor that this project duplicates a prior project.
Which of the following is a web template that is used to create websites?
A. ERP
B. CRM
C. EDRMS
D. CMS
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
A. Smoke test
B. Stress test
C. Penetration test
D. Regression test
A project manager is performing planning tasks for a complex project at a small company. Which of the following items would be of GREATEST importance during planning?
A. Defining the project objectives, scope, and success criteria
B. Assessing the resources available for operational support after project implementation
C. Providing updates and status reports to the project owner and stakeholders
D. Developing a records management plan and reviewing existing project artifacts
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to identify the level of engagement among project team members. Which of the following would be the BEST tool for the project manager to use?
A. Meeting chat
B. Email
C. Real-time survey
D. Whiteboard
While defining technical requirements, the development team requested a tiered architecture setup. Which of the following types of environments BEST describes this architecture?
A. Security environment
B. Network environment
C. Release environment
D. Stage environment
A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of the management team was requested on time. Which of the following documents should be reviewed to understand the root cause of this situation?
A. RACI
B. SOW
C. Escalation path
D. Communication plan
During the kickoff meeting, a stakeholder raises a concern that an assigned responsibility is outside of the stakeholder's domain. Which of the following would MOST likely be the reason?
A. The communication plan is outdated.
B. The project manager did not assess the stakeholders.
C. The project manager did not update the risk register.
D. The statement of work does not reflect the impacted stakeholders.
The project kickoff concluded, and the sponsor indicated that the recently hired summer interns are authorized to work on the project. Which of the following should the project manager do NEXT?
A. Host a risk workshop with all stakeholders to complete an initial risk assessment.
B. Work with the interns to develop a work breakdown structure and project schedule.
C. Conduct a skills assessment to determine the strengths and weaknesses of the staff.
D. Assign the resources to project tasks and encourage them to begin work immediately.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.