Skip to main content

PFMP Real Exam Questions

Portfolio Management Professional (PfMP)

495 questions available · Page 1 of 50

Updated Exam DumpsVerified AnswersPass Guarantee

Get Complete Exam Dumps
Question 1 Single choice

You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency.

Which of the following techniques uses historical data to determine if resource requirements have been consistently underestimated?

  1. A

    Lessons Learned Analysis

  2. B

    Requirements Analysis

  3. C

    Trend Analysis

  4. D

    Value Scoring & Measurement

Show answer and explanation

Correct answer: C

Question 2 Single choice

Having worked in portfolio management before, you are pleased you were selected to implement it and be the portfolio manager for your motorcycle company, well known throughout the world. As it is a new function, you worked with the Enterprise Program Management Office to ensure you had a complete inventory of the work in progress. Now as you prepared your various portfolio management artifacts, and have a Portfolio Review Board meeting upcoming in two weeks, sponsors will be proposing new components. This means:

  1. A

    A master schedule of resource allocation is needed

  2. B

    The meeting also should focus on reviewing existing components to see if they are aligned with current strategy

  3. C

    People throughout the organization should know about this meeting and its decisions

  4. D

    The meeting should have a set agenda, and each member should be contacted before it to learn of key issues

Show answer and explanation

Correct answer: A

Question 3 Single choice

Aligning the portfolio with the strategic objectives starts by developing the Portfolio Strategic Plan. You are currently developing this plan and are looking for a document that provides you long-term direction.

What are you looking for in this case?

  1. A

    Portfolio Strategic Plan

  2. B

    Inventory of Work

  3. C

    Portfolio Process Assets (PPAs)

  4. D

    Organizational strategy and objectives

Show answer and explanation

Correct answer: D

Question 4 Single choice

Different stakeholders will have different portfolio reporting requirements. Sponsors for example will have a great interest in:

  1. A

    If the portfolio will meet organizational strategy

  2. B

    Status in achieving benefits

  3. C

    Overall portfolio value

  4. D

    Status in terms of other authorized components

Show answer and explanation

Correct answer: B

Question 5 Single choice

Each portfolio risk should have a designated person as its owner. As the portfolio manager assigns the owner, the main responsibility is to:

  1. A

    Analyze the risk for its overall impact on portfolio success

  2. B

    Determine an appropriate response and implement it as soon as the risk occurs

  3. C

    Monitor the situation as long as the risk is current

  4. D

    Strive to take a negative risk and turn it into a positive opportunity

Show answer and explanation

Correct answer: C

Question 6 Single choice

While managing portfolio value, you met with stakeholders and discussed how to address the strengths and weaknesses in order to ensure benefits are comprehensively and holistically taken into consideration.

Which of the following tools and techniques are you performing?

  1. A

    Quantitative & Qualitative

  2. B

    SWOT

  3. C

    Benefits Realization

  4. D

    Value Scoring & Measurement

Show answer and explanation

Correct answer: B

Question 7 Single choice

You want to ensure that the Portfolio Review Board is able to make key decisions at each meeting. As the portfolio manager, you and your staff are responsible for scheduling the meetings, providing the agenda, taking minutes, tracking open issues, and documenting and communicating decisions that are made to key stakeholders. Before each meeting, you feel it is a best practice to:

  1. A

    Evaluate if the benefits of the portfolio are aligned with organizational strategy

  2. B

    Provide information about the status of each component of the portfolio

  3. C

    Use a balanced scorecard approach to show contribution to strategy

  4. D

    Provide a 'traffic light' approach to show components by category

Show answer and explanation

Correct answer: A

Question 8 Single choice

The portfolio management process ensures the components are aligned to goals.
However, it is driven by:

  1. A

    Viability

  2. B

    Value and benefits

  3. C

    Organizational strategy and objectives

  4. D

    Interdependencies and resource constraints

Show answer and explanation

Correct answer: C

Question 9 Single choice

Your organization, given the economic downturn in your country, decided to reduce its staff by 90% and outsource all operational activities including those of program and project managers and their teams. It has, however, retained the portfolio manager, and it has a Portfolio Review Board comprised of senior executives that meets monthly. Since outsourcing is the norm and not the exception, the manager of Procurement and Contracting is a major stakeholder. Her areas of interest are:

  1. A

    Benefits and outcomes toward strategic goals

  2. B

    Overall portfolio performance

  3. C

    Financial standing

  4. D

    Change decisions

Show answer and explanation

Correct answer: C

Question 10 Single choice

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team handle this strategic change.

Which of the following can serve as input here?

  1. A

    Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Portfolio Process Assets, Organizational
    Process Assets

  2. B

    Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Organizational Process Assets, Portfolio
    Management Plan

  3. C

    Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Portfolio Process Assets, Portfolio

  4. D

    Portfolio Strategic Plan, Portfolio Management Plan, Portfolio Roadmap, Portfolio Charter,Portfolio
    Process Assets, Portfolio

Show answer and explanation

Correct answer: D