  • Question 31:

    Which of the following has the GREATEST impact on the effectiveness of an HVAC system?

    A. Rooftop chiller size

    B. Wall insulation type

    C. Window treatments

    D. Occupancy load

  • Question 32:

    In a legal dispute between a client and a designer, a letter of agreement is considered __________.

    A. Negotiable

    B. Nonnegotiable

    C. Legally binding

    D. Binding following arbitration

  • Question 33:

    You have designed a small auditorium for an office building with access from the seating area to the stage to permit wheelchair access to the stage without leaving the auditorium. Your client wishes to remove the wheelchair access.

    How should you proceed?

    A. Write a letter advising the client that ADA guidelines are being violated against your advice, and place a copy of the letter in the job file.

    B. Inform the building department that you are not being permitted to design in compliance with ADA guidelines.

    C. Inform the client that you will be terminating work on this portion of the project until the issue can be resolved by arbitration.

    D. Accept the client's position and redesign the auditorium as directed

  • Question 34:

    Your client has a very limited budget for design services, and the scope of the project warrants mechanical and electrical engineering specification.

    What should you do?

    A. Reduce your scope to reduce the fee, and contract with a mechanical/electrical engineer for an outline specification.

    B. Recommend that the client work with a contractor to provide design-build services for mechanical/ electrical work.

    C. Request that the client contract directly with a mechanical/electrical engineer for limited services to review your drawings.

    D. Insist that your client increase the design budget to cover the necessary mechanical/electrical design services.

  • Question 35:

    Why is it necessary to indicate the placement of the proposed elevator and stairway in a preliminary plan?

    A. To ensure an acceptable location to meet all codes

    B. To verify the client's budget constraints

    C. To establish the structural support work required

    D. To ensure accessibility and visibility to visitors

  • Question 36:

    In which space is emergency lighting REQUIRED?

    A. Elevators

    B. Private offices

    C. Egress corridors

    D. Restrooms

  • Question 37:

    After construction on a project has begun, the client asks you to change the wallcovering originally specified to one that does not meet current code requirements.

    Which of the following is your BEST course of action?

    A. Research available products that are similar to the requested product and meet the code requirements. Present the options to the client for approval.

    B. Write a letter to the client stating that the change is against your professional recommendation and that you will make the change but assume no liability.

    C. Write a letter to the client explaining that you will not make the requested change.

    D. Tell the client that you will remove the wallcovering from the project and that the client may select and install a different product after your work is completed.

  • Question 38:

    How do you ensure that all signage on a construction project will be installed in the correct locations?

    A. Plan to be on site during installation of the signage, and specify where each sign will be placed.

    B. Require the signage vendor to provide detailed specifications.

    C. Provide a detailed takeoff along with a floor plan for installation.

    D. Schedule a meeting for the client or building owner to specify where signage will be placed.

  • Question 39:

    What aspect of working drawings can lead to problems during construction?

    A. Proprietary finishes

    B. Too much information

    C. Too many sheets of details

    D. Duplicated details

  • Question 40:

    In which situation should you use a construction change directive?

    A. To request an electrical contractor not listed by the contractor in the bid [tender] documents

    B. To request pricing for an additional receptacle per the client's request

    C. To provide additional dimensions to the contractor regarding a receptacle location

    D. To relocate an electrical receptacle because of revised furniture plans

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Test Prep exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your NCIDQ exam preparations and Test Prep certification application, do not hesitate to visit our Vcedump.com to find your solutions here.